 Frequency of use .Selection of the equipment should take into account a range of factors such as ground conditions.This is  should also be provided to contractors before any work commences.

Scaffolding is  inspected by a competent person:




  • After bad or excessively wet weather or high winds
  • Before it is put into use
  • Another event likely to have effected its strength 
  • At seven day intervals until it is dismantled
  • After any substantial additions or other alterations

                        